Public consultation for HKIA Master Plan 2030
![<p><span>Public consultation for </span><em>HKIA Master Plan 2030</em></p>](/media/1860/2011_1.jpg)
Approval of the Environmental Impact Assessment report and issuance of the Environmental Permit
Establishment of the Marine Ecology Enhancement Fund and Fisheries Enhancement Fund
Construction of the three-runway system began
![<p>Construction of the three-runway system began</p>](/media/1861/2016.jpg)
Construction of the sea wall commenced
![<p>Construction of the sea wall commenced</p>](/media/1867/construction-seawall-commenced.jpg)
Completion of the installation of two new, 5.2-kilometre aviation fuel pipelines, using the environmentally friendly horizontal directional drilling technique
![<p>Completion of the installation of two new, 5.2-kilometre aviation fuel pipelines, using the environmentally friendly horizontal directional drilling technique</p>](/media/1862/2018.jpg)
Construction of the new Automated People Mover depot completed
![<p>Construction of the new Automated People Mover depot completed</p>](/media/1864/apm-depot-completion.jpg)
Handover of the first parcel of land from the main reclamation contractor to the follow-on contractor to build airfield infrastructure and construction support facilities
![<p>Handover of the first parcel of land from the main reclamation contractor to the follow-on contractor to build airfield infrastructure and construction support facilities</p>](/media/1865/b1-handover-area-b1-01-dji_0140.jpg)
Construction of the new North Runway commenced
![<p>Construction of the new North Runway commenced</p>](/media/1866/construction-of-runway-commenced.jpg)
The original North Runway re-designated as Centre Runway
![<p><span>The original North Runway re-designated as Centre Runway</span></p>](/media/1949/pr_1573_new-runway-designation_1.jpg)
Completion of the pavement of the Third Runway
![<p>Completion of the pavement of the Third Runway</p>](/media/1909/pr_1560_1_ce_chairman_ceo_01.jpg)
Superstructure construction for the expansion of Terminal 2 commences
The Third Runway at HKIA commissioned
![<p>The Third Runway at HKIA commissioned</p>](/media/1992/pr_1619_water_salute.jpg)
Operation familiarisation for aircraft take-offs and landings on the Third Runway commenced
![<p>Operation familiarisation for aircraft take-offs and landings on the Third Runway commenced</p>](/media/1974/pr_1602_operation-familiarisation_1.jpg)
Closure of Centre Runway for reconfiguration
Aerodrome licence for operation of HKIA renewed to include the Third Runway and associated taxiways
![<p>Aerodrome licence for operation of HKIA renewed to include the Third Runway and associated taxiways</p>](/media/1962/pr_1597_ceo.jpg)
The flight check of the Third Runway completed
![<p>The flight check of the Third Runway completed</p>](/media/1958/pr_1590_flight_check_1.jpg)
Completion of the Three-runway System
Completion of the Automated People Mover and Baggage Handling System
Completion of the T2 Concourse and Terminal 2 expansion